Gas Works update

Triio is at present working in Meadway replacing services and supplies to all residents with the anticipation of having this section completed by 2/12/19

Regarding Stockens Green we have completed 90% of the this section, connection point only to be completed at the Junction of Wadnall Way and Stockens Green

Triio will be carrying on with the works in Wadnall Way up until Christmas holiday 20/12/19 with all excavations being backfilled and reinstated for the Christmas holidays

Works in Park Lane have been suspended due to Safety Reasons, the road is too narrow for operatives to work safely. It is now proposing to close this section off Park Lane in February From Junction of Deards end lane to the Junction of Gipsy Lane, we are in talks with the local Authorities regarding these works.